Laxminarayan Arcade
Completion date passedWai (M Cl), Satara 412803 |Promoter: Rajan Namdeo Pore
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Oct 2023
P52700019419The latest completion date on record passed 3 years ago.
- Registered
- 29 Jan 2019
- Promised
- 30 Oct 2023
Completion promised for 30 Oct 2023
P52700019452The latest completion date on record passed 3 years ago.
- Registered
- 1 Feb 2019
- Promised
- 30 Oct 2023
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52700019419 | 29 Jan 2019 | 30 Oct 2023 | — | Rajan Namdeo Pore | Project page |
| P52700019452 | 1 Feb 2019 | 30 Oct 2023 | — | Rajan Namdeo Pore | Project page |
Documents
2 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.