Raj Realtors (A Project By Raj Group)
Deedo IDDD-DP9COf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 42 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Tulsi V City - Tulsi VivaanRegulatory order: PROJECT NAME:TULSI V CITY - TULSI VIVAAN (Regulatory Case No. 201 OF 2024) dated 30 May 2024. | 30 May 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Tulsi V City - Tulsi VivaanP52000015825 | Pashane | Certificate Signed | 30 Sep 2021 | 31 Mar 2025 | +42 mo |
Raj Realtors (A Project By Raj Group), in questions
Does Raj Realtors (A Project By Raj Group) finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 42 mo late. Across Maharashtra, 73% kept their date.
How many projects has Raj Realtors (A Project By Raj Group) registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Raj Realtors (A Project By Raj Group) have MahaRERA regulatory cases?
1 regulatory case name its registrations.