Individual promoter · first RERA registration 2017

Radheyshyam Roshanlal Gupta

Deedo IDDD-YE0S

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 82 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay82 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Radheshyam RoyalP51700006917Thane (M Corp.)Certificate Signed31 Dec 20197 Aug 2024+82 mo*

Radheyshyam Roshanlal Gupta, in questions

Does Radheyshyam Roshanlal Gupta finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 82 mo late. Across Maharashtra, 73% kept their date.

How many projects has Radheyshyam Roshanlal Gupta registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Radheyshyam Roshanlal Gupta have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology