Rachana Enterprises
Deedo IDDD-NHF3Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Yash Enclaves Bldg 3P51700004472 | Dombivli | Certificate Signed | 30 Dec 2020 | 30 Dec 2021 | +12 mo |
| Aparna Co-operative Housing Society LimitedP51700051856 | Dombivli | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
Rachana Enterprises, in questions
Does Rachana Enterprises finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Rachana Enterprises registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Rachana Enterprises have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.