Skip to content
Individual promoter · first RERA registration 2024

Raaz Mohammed Abdul Samad Pathan

Deedo IDDD-CG2J

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Muktangan ResidencyP51800054585DahisarCertificate Signed31 Oct 202729 Feb 2028+4 mo

Raaz Mohammed Abdul Samad Pathan, in questions

Does Raaz Mohammed Abdul Samad Pathan finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has Raaz Mohammed Abdul Samad Pathan registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Raaz Mohammed Abdul Samad Pathan have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology