Skip to content
Company or firm · first RERA registration 2023

R Sandesh And Soham Developers

Deedo IDDD-X9A1

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 1 registration with dates has moved or missed its RERA date

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Soham And Sandesh CityP50500054149KanholiCertificate Signed31 Mar 202931 Mar 2029On date

R Sandesh And Soham Developers, in questions

Does R Sandesh And Soham Developers finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has R Sandesh And Soham Developers registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does R Sandesh And Soham Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology