Puranik Buildcon Private Limited
Deedo IDDD-NDG0Of 5 registrations whose promised date has arrived, 4 kept it (80%). The rest ran a median 4 mo late.
Delivery record
6 of 11 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 11 registrations
11 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Puraniks Abitante Phase 1AP52100000437 | Bavadhan Bk | Certificate Signed | 30 Jun 2022 | 30 Jun 2022 | On date |
| Aldea EspanolaP52100000537 | Mahalunge | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Puraniks Abitante Phase 1BP52100000569 | Bavadhan Bk | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Aldea EspanolaP52100000572 | Mahalunge | Certificate Signed | 30 Mar 2022 | 30 Mar 2022 | On date |
| Aldea Espanola Phase VIIP52100004340 | Mahalunge | Certificate Signed | 30 Dec 2028 | 30 Dec 2028 | On date |
| Puraniks Abitante Fiore, Phase 2AP52100020202 | Bavadhan Bk | Certificate Signed | 30 Dec 2030 | 30 Apr 2031 | +4 mo |
| Puraniks Abitante Fiore, Phase 2BP52100020238 | Bavadhan Bk | Certificate Signed | 30 Dec 2030 | 30 Apr 2031 | +4 mo |
| Aldea Espanola Phase VIIIP52100024044 | Mahalunge | Certificate Signed | 30 Mar 2026 | 30 Mar 2026 | +8 mo* |
| Puraniks Abitante Fiore Phase 2CP52100048353 | Bavadhan Bk | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Puraniks Abitante Fiore Phase 2C1P52100049352 | Bavadhan Bk | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 mo |
| Puraniks Abitante Fiore Phase 2DPR1264042600284 | Bavadhan Bk | Certificate Signed | 31 Dec 2033 | 30 Apr 2034 | +4 mo |
Show all 11 registrationsShow fewer
Puranik Buildcon Private Limited, in questions
Does Puranik Buildcon Private Limited finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 4 kept it (80%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Puranik Buildcon Private Limited registered with MahaRERA?
10 projects under 11 MahaRERA registrations; 5 completed on MahaRERA.
Does Puranik Buildcon Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.