Pune Housing and Area Development Board Pune
Deedo IDDD-REZ4Of 16 registrations whose promised date has arrived, 9 kept it (56%). The rest ran a median 7 mo late.
Delivery record
13 of 22 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 22 registrations
22 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Quarterly progress report not filed | Construction of 160 EWS 84 LIG and 28 MIG T/s at Gat no 425/2 Part Kagal Dist Kolhapur under PMAYQuarterly progress report not filed: Construction of 160 EWS 84 LIG and 28 MIG T/s at Gat no 425/2 Part Kagal Dist Kolhapur under PMAY | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
Show all 22 registrationsShow fewer
Pune Housing and Area Development Board Pune, in questions
Does Pune Housing and Area Development Board Pune finish projects on time?
Of 16 MahaRERA registrations whose promised completion date has arrived, 9 kept it (56%). The rest ran a median 7 mo late. Across Maharashtra, 73% kept their date.
How many projects has Pune Housing and Area Development Board Pune registered with MahaRERA?
22 projects under 22 MahaRERA registrations; 9 completed on MahaRERA.
Does Pune Housing and Area Development Board Pune have MahaRERA regulatory cases?
1 regulatory case name its registrations.