Prithviraj Kakade Constructions Pvt Ltd
Deedo IDDD-FHPROf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 38 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dharti apartmentP53000047160 | Ujalaiwadi (Ct) | Certificate Signed | 1 Sep 2023 | 1 Sep 2023 | +38 mo* |
Prithviraj Kakade Constructions Pvt Ltd, in questions
Does Prithviraj Kakade Constructions Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 38 mo late. Across Maharashtra, 73% kept their date.
How many projects has Prithviraj Kakade Constructions Pvt Ltd registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Prithviraj Kakade Constructions Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.