Prithvi Edifice Pvt Ltd
Deedo IDDD-ZMHKOf 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Prithvi Presidio, Buiding B, Phase-1P52100002834 | Hadapsar | Certificate Signed | 31 Mar 2019 | 30 Sep 2022 | +92 mo* |
| Prithvi ProximusP52100021774 | Hadapsar | Certificate Signed | 31 Jul 2024 | 30 Jul 2025 | +28 mo* |
| Prithvi Presidio, Building B, Phase-2P52100030058 | Hadapsar | Certificate Signed | 31 Mar 2023 | 31 Mar 2023 | +44 mo* |
| Doctor HouseP52100055729 | Hadapsar | Certificate Signed | 30 Sep 2027 | 30 Sep 2027 | On date |
Prithvi Edifice Pvt Ltd, in questions
Does Prithvi Edifice Pvt Ltd finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 44 mo late. Across Maharashtra, 73% kept their date.
How many projects has Prithvi Edifice Pvt Ltd registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Prithvi Edifice Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.