Prithvi Edifice Pvt Ltd

Deedo IDDD-ZMHK

Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late.

Projects44 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay44 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Prithvi Presidio, Buiding B, Phase-1P52100002834HadapsarCertificate Signed31 Mar 201930 Sep 2022+92 mo*
Prithvi ProximusP52100021774HadapsarCertificate Signed31 Jul 202430 Jul 2025+28 mo*
Prithvi Presidio, Building B, Phase-2P52100030058HadapsarCertificate Signed31 Mar 202331 Mar 2023+44 mo*
Doctor HouseP52100055729HadapsarCertificate Signed30 Sep 202730 Sep 2027On date

Prithvi Edifice Pvt Ltd, in questions

Does Prithvi Edifice Pvt Ltd finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 44 mo late. Across Maharashtra, 73% kept their date.

How many projects has Prithvi Edifice Pvt Ltd registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.

Does Prithvi Edifice Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology