Pritesh Damji Savla
Deedo IDDD-YF8MOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 11 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Bhagwati AshishP51800010515 | Andheri | Certificate Signed | 1 Jun 2023 | 31 May 2024 | +11 mo |
| saroj sadan CHSLP51800012908 | Kurar | Certificate Signed | 15 Apr 2026 | 15 Apr 2026 | On date |
Pritesh Damji Savla, in questions
Does Pritesh Damji Savla finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Pritesh Damji Savla registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Pritesh Damji Savla have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.