Skip to content
Company or firm · first RERA registration 2018

Prime Smp Developers

Deedo IDDD-H2KX

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 22 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay22 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Destination HinjawadiP52100017252Hinjavadi (Ct)Certificate Signed30 Dec 202430 Dec 2024+22 mo*

Prime Smp Developers, in questions

Does Prime Smp Developers finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 22 mo late. Across Maharashtra, 73% kept their date.

How many projects has Prime Smp Developers registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Prime Smp Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology