Company or firm · first RERA registration 2023

Prime Builders And Developers

Deedo IDDD-918A

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 13 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay13 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Prime SolitaireP52000049635UlaweCertificate Signed31 Oct 202531 Oct 2025+13 mo*

Prime Builders And Developers, in questions

Does Prime Builders And Developers finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 13 mo late. Across Maharashtra, 73% kept their date.

How many projects has Prime Builders And Developers registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Prime Builders And Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology