Pride Ventures (I) Pvt Ltd

Deedo IDDD-7H4X

Of 3 registrations whose promised date has arrived, 3 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 3 registrations with dates has moved or missed its RERA date

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Pride Phoenix Building B1-B2P51500000331ChikalthanaCompleted31 Dec 2018—On date
Pride Phoenix Building C1-C2P51500000337ChikalthanaCompleted31 Dec 2019—On date
Pride PhoenixP51500000376ChikalthanaCertificate Signed31 Dec 201831 Dec 2018On date

Pride Ventures (I) Pvt Ltd, in questions

Does Pride Ventures (I) Pvt Ltd finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Pride Ventures (I) Pvt Ltd registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.

Does Pride Ventures (I) Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology