Prayeja City

Deedo IDDD-8VKS

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 40 mo late — longer than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay40 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Prayeja CityP52100010668Wadgaon BkCertificate Signed30 Nov 201830 Jun 2024+67 mo
Prayeja CityP52100011611Wadgaon BkCertificate Signed31 Dec 201831 Dec 2019+12 mo

Prayeja City, in questions

Does Prayeja City finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 40 mo late. Across Maharashtra, 73% kept their date.

How many projects has Prayeja City registered with MahaRERA?

1 project under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Prayeja City have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology