Pratham Infra
Deedo IDDD-MC63Of 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 12 mo late.
Delivery record
4 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Pratham Swami SamarthP52000021603 | Vadghar (Ct) | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | +41 mo* |
| Pratham Shree SamarthP52000022814 | Vadghar (Ct) | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | On date |
| Pratham PrideP52000025077 | Devad | Certificate Signed | 30 Mar 2024 | 29 Mar 2025 | +12 mo |
| New Gulmohar Co - Operative Housing SocietyP52000047149 | Panvel | Certificate Signed | 29 Dec 2024 | 31 Dec 2025 | +12 mo |
| Pratham VrundavanPR1270002502793 | Vakadi | Certificate Signed | 1 Dec 2029 | 1 Apr 2030 | +4 mo |
Pratham Infra, in questions
Does Pratham Infra finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Pratham Infra registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 3 completed on MahaRERA.
Does Pratham Infra have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.