Of 8 registrations whose promised date has arrived, 8 kept it (100%).

Projects1010 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 10 registrations with dates has moved or missed its RERA date

10 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Suresh smrutiP52800004093RahatagharCertificate Signed21 Jan 201821 Jan 2018On date
D. A. Bhosale PlazaP52800014818Nachane (Ct)Certificate Signed2 Apr 20222 Apr 2022On date
Omkar SankalpP52800015492Zadgaon CtCertificate Signed30 Apr 202330 Apr 2023On date
Dattakrupa ComplexP52800015815Nachane (Ct)Certificate Signed30 Apr 202330 Apr 2023On date
Omkar ShilpP52800021166Zadgaon CtCertificate Signed30 Mar 202330 Mar 2023On date
Omkar GovindP52800032027Nachane (Ct)Certificate Signed31 Oct 202331 Oct 2023On date
Omkar Rawool ParkP52800033013Nachane (Ct)Certificate Signed31 Dec 202631 Dec 2026On date
Omkar VishwaP52800033096RahatagharCertificate Signed31 Dec 202631 Dec 2026On date
Omkar SpandanP52800053099Nachane (Ct)Certificate Signed31 Aug 202531 Aug 2025On date
Omkar SwamikrupaP52800055210Ratnagiri (M Cl)Certificate Signed31 Mar 202531 Mar 2025On date

Prasad Prabhakar Waghdhare, in questions

Does Prasad Prabhakar Waghdhare finish projects on time?

Of 8 MahaRERA registrations whose promised completion date has arrived, 8 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Prasad Prabhakar Waghdhare registered with MahaRERA?

10 projects under 10 MahaRERA registrations; 10 completed on MahaRERA.

Does Prasad Prabhakar Waghdhare have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology