Company or firm · first RERA registration 2017

Prarthana Griha Nirman

Deedo IDDD-GY9H

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 17 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay17 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Rajkamal ParkP51900010115Ward FsouthCertificate Signed30 Dec 202331 May 2025+17 mo

Prarthana Griha Nirman, in questions

Does Prarthana Griha Nirman finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.

How many projects has Prarthana Griha Nirman registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Prarthana Griha Nirman have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology