Skip to content
Company or firm · first RERA registration 2021

Pramukh Developers

Deedo IDDD-H434

Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects77 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

4 registrations of 7 ran past the RERA date

Months late against the original RERA promise, per registration

7 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Patels SapphireP51700031089Ambarnath(M Cl)Certificate Signed31 Aug 202431 Aug 2024On date
Patels FalconP51700032547Ambarnath(M Cl)Certificate Signed31 Dec 202631 Dec 2026On date
Patels PhoenixP51700032731Ambarnath(M Cl)Certificate Signed30 Jun 202430 Jun 2025+12 mo
Patels EireneP51700054106Ambarnath(M Cl)Certificate Signed31 Aug 202631 Dec 2026+4 mo
Patels AspireP51700055979Ambarnath(M Cl)Certificate Signed31 Dec 202630 Apr 2027+4 mo
Patels AvenueP51700080725Ambarnath(M Cl)Certificate Signed31 Mar 202831 Jul 2028+4 mo
Patels SkylinePM1180002602379VarsovaNot on record30 Sep 2030—On date