Patels Eirene

Certificate Signed

Ambarnath(M Cl), Thane 421501 |Promoter: Pramukh Developers

Residential / Group HousingRERAP51700054106
27 Dec 2023Registered with MahaRERA
31 Aug 2026Promised completion
31 Dec 2026Revised completionPushed back 4 months
1Building
60Units registered31 booked (52%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 1RK, 2BHK, 3BHK60 units in all
Address
Plot No 277 Cts No 4483 To 4488 Plot No 280 Cts No 4471 To 4476, Kansai Section, Ambernath EastPIN 421501
Designated bank account
82
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.20934, 73.17743
Patels Eirene is at latitude 19.20934, longitude 73.17743.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
27 Dec 2023
Promised
31 Aug 2026
Revised
31 Dec 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005410627 Dec 202331 Aug 202631 Dec 2026Pramukh DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Patels Eirene760

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

31 of 60 units booked (52%), as the promoter reported to MahaRERA

1BHK · 29 units1RK · 1 unit2BHK · 29 units3BHK · 1 unit
TypeCarpet areaUnitsBooked
1BHK28.71 sq m · 309 sq ft11
1BHK30.01 sq m · 323 sq ft52
1BHK30.1 sq m · 324 sq ft66
1BHK30.57 sq m · 329 sq ft52
1BHK32.7 sq m · 352 sq ft117
1BHK32.98 sq m · 355 sq ft11
1RK22.02 sq m · 237 sq ft11
2BHK35.02 sq m · 377 sq ft62
Show all 16 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK35.86 sq m · 386 sq ft51
2BHK37.16 sq m · 400 sq ft11
2BHK37.75 sq m · 406 sq ft10
2BHK37.9 sq m · 408 sq ft61
2BHK40.05 sq m · 431 sq ft10
2BHK40.13 sq m · 432 sq ft42
2BHK43.2 sq m · 465 sq ft53
3BHK53.88 sq m · 580 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 100 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPramukh Developers PAN.pdf · uploaded 31 Aug 2023Source

Legal

  • Legal Title reportEIRENE TITLE.pdf · uploaded 31 Aug 2023Source
  • Declaration Form BEIRENE FORM B.pdf · uploaded 31 Aug 2023Source
  • Other – LegalEIRENE AFS 21NOV2023.pdf · uploaded 21 Nov 2023Source

Migrated

  • 1 PAN CardPramukh Developers PAN.pdf · uploaded 31 Aug 2023Source
  • 1 Copy of the legal title reportEIRENE TITLE.pdf · uploaded 31 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentEIRENE CC.pdf · uploaded 31 Aug 2023Source
Show all 101 documentsShow fewer documents

Migrated

  • 1 Declaration in FORM BEIRENE FORM B.pdf · uploaded 31 Aug 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)EIRENE FORM1.pdf · uploaded 31 Aug 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)EIRENE FORM2.pdf · uploaded 31 Aug 2023Source
  • 1 Proforma of Allotment letterEirene Allotment Letter Format.pdf · uploaded 31 Aug 2023Source
  • 1 Declaration about Commencement CertificateEIRENE DECLARATION OF CC.pdf · uploaded 7 Oct 2023Source
  • 1 a Details of encumbrances concerned to FinanceEIRENE NON ENCB.pdf · uploaded 8 Oct 2023Source
  • 1 b Details of encumbrances concerned to LegalEIRENE NON ENCB.pdf · uploaded 8 Oct 2023Source
  • 1 CERSAI detailsEIRENE NO CERSAI.pdf · uploaded 8 Oct 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsEIRENE DISCLOSURE OF INTEREST.pdf · uploaded 8 Oct 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameEIRENE BANK DETAILS.pdf · uploaded 8 Oct 2023Source
  • 1 Deviation Report with respect to Allotment letterEIRENE DEVIATION AL.pdf · uploaded 8 Oct 2023Source
  • 1 Copy of Layout Approval (in case of layout)EIRENE CC PLAN.pdf · uploaded 16 Oct 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form3.pdf · uploaded 16 Oct 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentEIRENE CC PLAN.pdf · uploaded 18 Oct 2023Source
  • 1 Other – LegalEIRENE AFS 21NOV2023.pdf · uploaded 21 Nov 2023Source
  • 2 a Details of encumbrances concerned to FinanceEIRENE NON ENC.pdf · uploaded 6 Dec 2023Source
  • 2 b Details of encumbrances concerned to LegalEIRENE NON ENC.pdf · uploaded 6 Dec 2023Source
  • 1 Proforma of Agreement for saleeirene afs.pdf · uploaded 11 Dec 2023Source
  • 1 Deviation Report with respect to model copy of AgreementEIRENE DEVIATION AFS.pdf · uploaded 11 Dec 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)EireneForm1Mar24.pdf · uploaded 4 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)EireneForm3Mar24.pdf · uploaded 4 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)EireneForm2Mar24.pdf · uploaded 4 Dec 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)EireneForm1Jun24.pdf · uploaded 18 Dec 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)EireneForm1Sept24.pdf · uploaded 18 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)EirenForm3Jun24.pdf · uploaded 18 Dec 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)EireneForm3Sept24.pdf · uploaded 18 Dec 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)EireneForm2Jun24.pdf · uploaded 18 Dec 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)EireneForm2Sept24.pdf · uploaded 18 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)EIRENEFORM5MAR24.pdf · uploaded 8 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)EIRENEFORM1DEC24.pdf · uploaded 19 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)EIRENEFORM3DEC24.pdf · uploaded 19 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)EIRENEFORM2DEC24.pdf · uploaded 19 Feb 2025Source
  • Form 1EireneForm1Mar2025.pdf · uploaded 20 May 2025Source
  • Form 2EireneForm2Mar2025.pdf · uploaded 20 May 2025Source
  • Form 3EireneForm3Mar25.pdf · uploaded 20 May 2025Source
  • Form 5 (FY 2024-2025)EIRENE FORM5 31MAR25.pdf · uploaded 29 Sep 2025Source
  • Form 1EIRENE FORM1.pdf · uploaded 10 Jun 2026Source
  • Form 2EIRENE FORM2.pdf · uploaded 10 Jun 2026Source
  • Form 3EIRENE FORM3_compressed.pdf · uploaded 10 Jun 2026Source
  • Disclosure of Sold and Booked Inventorysold un sold units as on dec 2023.pdf · uploaded 10 Jun 2026Source
  • Form 1EireneForm1Jun24.pdf · uploaded 10 Jun 2026Source
  • Form 2EireneForm2Jun24.pdf · uploaded 10 Jun 2026Source
  • Form 3EirenForm3Jun24.pdf · uploaded 10 Jun 2026Source
  • Disclosure of Sold and Booked Inventorysold un sold units as on june 2024.pdf · uploaded 10 Jun 2026Source
  • Disclosure of Sold and Booked Inventorysold un sold units as on sep 2024.pdf · uploaded 10 Jun 2026Source
  • Form 1EireneForm1Sept24.pdf · uploaded 10 Jun 2026Source
  • Form 2EireneForm2Sept24.pdf · uploaded 10 Jun 2026Source
  • Form 3EireneForm3Sept24.pdf · uploaded 10 Jun 2026Source
  • Form 1EIRENEFORM1DEC24.pdf · uploaded 10 Jun 2026Source
  • Form 2EIRENEFORM2DEC24.pdf · uploaded 10 Jun 2026Source
  • Form 3EIRENEFORM3DEC24.pdf · uploaded 10 Jun 2026Source
  • Disclosure of Sold and Booked Inventorysold un sold units as on dec 2024.pdf · uploaded 10 Jun 2026Source
  • Disclosure of Sold and Booked Inventorysold un sold units as on mar 2025.pdf · uploaded 10 Jun 2026Source
  • Form 1EireneForm1Mar2025.pdf · uploaded 10 Jun 2026Source
  • Form 2EireneForm2Mar2025.pdf · uploaded 10 Jun 2026Source
  • Form 3EireneForm3Mar25.pdf · uploaded 10 Jun 2026Source
  • Form 1EIRENE FORM1 30JUNE25.pdf · uploaded 17 Jul 2026Source
  • Form 2EIRENE FORM2 30JUN25.pdf · uploaded 17 Jul 2026Source
  • Form 3EIRENE FORM3 30JUNE25.pdf · uploaded 17 Jul 2026Source
  • Disclosure of Sold and Booked InventoryEIRENE SOLD BOOKED30JUNE25.pdf · uploaded 17 Jul 2026Source
  • Form 1EIRENE FORM1 30SEP25.pdf · uploaded 17 Jul 2026Source
  • Form 2EIRENE FORM2 30SEP25.pdf · uploaded 17 Jul 2026Source
  • Form 3EIRENE FORM3 30SEP25.pdf · uploaded 17 Jul 2026Source
  • Disclosure of Sold and Booked InventoryEIRENE SOLD BOOKED 30SEP25.pdf · uploaded 17 Jul 2026Source
  • Form 1EIRENE FORM1 DEC25.pdf · uploaded 17 Jul 2026Source
  • Form 2EIRENE FORM2 DEC25.pdf · uploaded 17 Jul 2026Source
  • Form 3EIRENE FORM3 DEC25.pdf · uploaded 17 Jul 2026Source
  • Disclosure of Sold and Booked InventoryEIRENE SOLD BOOKED 30SEP25.pdf · uploaded 17 Jul 2026Source
  • Form 1EIRENE FORM1 MAR26.pdf · uploaded 17 Jul 2026Source
  • Form 2EIRENE FORM2 MAR26.pdf · uploaded 17 Jul 2026Source
  • Form 3EIRENE FORM3 MAR26.pdf · uploaded 17 Jul 2026Source
  • Disclosure of Sold and Booked InventoryEIRENE SOLD BOOKED 30SEP25.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 1EIRENE FORM1 30JUNE26.pdf · uploaded 31 Aug 2026Source
  • Withdrawal Update Form 2EIRENE FORM2 30JUNE26.pdf · uploaded 31 Aug 2026Source
  • Withdrawal Update Form 3EIRENE FORM3 30JUNE26.pdf · uploaded 31 Aug 2026Source
  • Form 2A (FY 2023-2024)EIRENE FORM2A 31MAR24.pdf · uploaded 9 Sep 2026Source
  • Form 2A (FY 2024-2025)EIRENE FORM2A 31MAR25.pdf · uploaded 9 Sep 2026Source
  • Form 2A (FY 2025-2026)EIRENE FORM2A 31MAR26.pdf · uploaded 9 Sep 2026Source
  • Form 2A (FY 2026-2027)EIRENE FORM2A 04SEP26.pdf · uploaded 9 Sep 2026Source
  • Form 5 (FY 2023-2024)EIRENE FORM5 31MAR24.pdf · uploaded 10 Sep 2026Source
  • Form 5 (FY 2025-2026)EIRENE FORM5 31MAR26.pdf · uploaded 15 Sep 2026Source

Technical

  • DocumentEIRENE CC PLAN.pdf · uploaded 16 Oct 2023Source
  • DocumentEIRENE CC PLAN.pdf · uploaded 18 Oct 2023Source

Technical (Architect)

  • DocumentEireneForm1Mar24.pdf · uploaded 4 Dec 2024Source
  • DocumentEireneForm1Jun24.pdf · uploaded 18 Dec 2024Source
  • DocumentEireneForm1Sept24.pdf · uploaded 18 Dec 2024Source
  • DocumentEIRENEFORM1DEC24.pdf · uploaded 19 Feb 2025Source
  • DocumentEIRENE FORM1 30JUNE26.pdf · uploaded 26 Aug 2026Source

Technical (Engineer)

  • DocumentEireneForm2Mar24.pdf · uploaded 4 Dec 2024Source
  • DocumentEireneForm2Jun24.pdf · uploaded 18 Dec 2024Source
  • DocumentEireneForm2Sept24.pdf · uploaded 18 Dec 2024Source
  • DocumentEIRENEFORM2DEC24.pdf · uploaded 19 Feb 2025Source
  • DocumentEIRENE FORM2 30JUNE26.pdf · uploaded 26 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Ambarnath(M Cl), Ambarnath taluka

Survey, CTS, gat or plot numbers

PLOT NO 277 CTS NO 4483 TO 4488 PLOT NO 280 CTS NO 4471 TO 4476

Boundaries

North
Road
South
Road
East
Plot No 276
West
Plot No 278

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMahesh Jagtap And Associates—
Chartered accountantD H Purohit & Associates—
Chartered accountantRpmg & Associates—
EngineerGanesh Patil—
EngineerM/S S V Patel & Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology