Company or firm · first RERA registration 2017

Prakash Realty

Deedo IDDD-EZNN

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 14 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay14 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Ganraya Mall phase1 wing BP52100005707Daund (M Cl)Certificate Signed31 Dec 201930 Dec 2021+24 mo
NakshatraPR1261012502932Daund (M Cl)Certificate Signed31 Dec 202930 Apr 2030+4 mo

Prakash Realty, in questions

Does Prakash Realty finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 14 mo late. Across Maharashtra, 73% kept their date.

How many projects has Prakash Realty registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Prakash Realty have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology