Polo Infra Developers Private Limited
Deedo IDDD-SMXSOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gopal Terrace Co-operative Housing Society LTDP51800050616 | Eksar | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 mo |
| Polo MatrixP51800054588 | Malad | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Polo Infra Developers Private Limited, in questions
Does Polo Infra Developers Private Limited finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Polo Infra Developers Private Limited registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Polo Infra Developers Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.