Company or firm · first RERA registration 2018
Pinnac Anand Associates
Deedo IDDD-09SFNone of 1 registration has reached its promised completion date yet.
Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record36registered first-sale deeds matched so far
Regulatory cases0none on record
Delivery record
None of 1 registration with dates has moved or missed its RERA date
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| West End Residency Wing EP52100015619 | Warje | Certificate Signed | 20 Jan 2027 | 31 Jul 2025 | On date |
Pinnac Anand Associates, in questions
Does Pinnac Anand Associates finish projects on time?
None of its 1 MahaRERA registration has reached its promised completion date yet.
How many projects has Pinnac Anand Associates registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Pinnac Anand Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology