Pawar Group
Deedo IDDD-R2X9Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 17 mo late.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Ganesh ParadiseP51700017680 | Badlapur | Certificate Signed | 15 Feb 2021 | 15 Feb 2021 | On date |
| Shree Ganesh SymphonyP51700025109 | Badlapur | Certificate Signed | 1 Dec 2025 | 1 Dec 2025 | +11 mo* |
| Shree Ganesh Symphony Wing CP51700050772 | Ambarnath | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
| Seventh AvenueP51700055291 | Badlapur (M Cl) | Active | 31 Dec 2031 | — | On date |
Pawar Group, in questions
Does Pawar Group finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.
How many projects has Pawar Group registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does Pawar Group have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.