Pavan Hastimal Jain
Deedo IDDD-7REHOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 41 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Khushi ApartmentP51700026552 | Navi Mumbai (M Corp.) | Certificate Signed | 22 May 2023 | 22 May 2023 | +41 mo* |
Pavan Hastimal Jain, in questions
Does Pavan Hastimal Jain finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 41 mo late. Across Maharashtra, 73% kept their date.
How many projects has Pavan Hastimal Jain registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Pavan Hastimal Jain have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.