Company or firm · first RERA registration 2017

Patki-Joshi Engineers and Contractors Pvt. Ltd

Deedo IDDD-RYB2

Of 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.

Projects44 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay24 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vishwa PrestigeP53000001706Kolhapur (M Corp.)Certificate Signed31 Dec 201731 Dec 2017On date
Vishwa Nest ApartmentsP53000015053Kolhapur (M Corp.)Certificate Signed31 Mar 202030 Mar 2022+24 mo
Vishwa Vastu ApartmentsP53000020255Kolhapur (M Corp.)Certificate Signed30 Apr 202230 Apr 2022On date
Vishwa Ram-SnehP53000046648Kolhapur (M Corp.)Certificate Signed30 Jun 202530 Jun 2025On date

Patki-Joshi Engineers and Contractors Pvt. Ltd, in questions

Does Patki-Joshi Engineers and Contractors Pvt. Ltd finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 3 kept it (75%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.

How many projects has Patki-Joshi Engineers and Contractors Pvt. Ltd registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 4 completed on MahaRERA.

Does Patki-Joshi Engineers and Contractors Pvt. Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology