Panchshil Infrastructure Holdings Pvt. Ltd

Deedo IDDD-Y3G8

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 38 mo late.

Projects55 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay38 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases8no insolvency

Delivery record

1 of 5 registrations with dates moved or missed their RERA date · months late against the original promise

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Panchshil TowersP52100002528WagholiCompleted30 Dec 202630 Dec 2026On date
T-VillaP52100010632WagholiCertificate Signed30 Sep 202330 Sep 2023+38 mo*
SohoP52100017890WagholiCertificate Signed30 Dec 202630 Dec 2026On date
V2 Villa P-1P52100034062WagholiCertificate Signed31 Dec 202731 Dec 2027On date
V3 Villa Phase- IIP52100052083WagholiCertificate Signed31 Dec 202731 Dec 2027On date

Panchshil Infrastructure Holdings Pvt. Ltd, in questions

Does Panchshil Infrastructure Holdings Pvt. Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 38 mo late. Across Maharashtra, 73% kept their date.

How many projects has Panchshil Infrastructure Holdings Pvt. Ltd registered with MahaRERA?

5 projects under 5 MahaRERA registrations; 3 completed on MahaRERA.

Does Panchshil Infrastructure Holdings Pvt. Ltd have MahaRERA regulatory cases?

8 regulatory cases name its registrations.