Company or firm · first RERA registration 2017
Panchshil Infrastructure Holdings Pvt. Ltd
Deedo IDDD-Y3G8Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 38 mo late.
Projects55 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay38 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases8no insolvency
Delivery record
1 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | T-VillaDeregistered: T-Villa | Not on record |
| complaint | Panchshil TowersComplaint CC005000000043716 | Not on record |
| complaint | Panchshil TowersComplaint CC005000000053905 | Not on record |
| complaint | Panchshil TowersComplaint CC005000000198197 | Not on record |
| complaint | Panchshil TowersComplaint CC005000000259052 | Not on record |
| complaint | Panchshil TowersComplaint CC12504411 | Not on record |
| appeal | Panchshil TowersAppeal AT005000000063831/22 | Not on record |
| appeal | Panchshil TowersAppeal AT005000000063819/22 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Panchshil TowersP52100002528 | Wagholi | Completed | 30 Dec 2026 | 30 Dec 2026 | On date |
| T-VillaP52100010632 | Wagholi | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | +38 mo* |
| SohoP52100017890 | Wagholi | Certificate Signed | 30 Dec 2026 | 30 Dec 2026 | On date |
| V2 Villa P-1P52100034062 | Wagholi | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
| V3 Villa Phase- IIP52100052083 | Wagholi | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
Panchshil Infrastructure Holdings Pvt. Ltd, in questions
Does Panchshil Infrastructure Holdings Pvt. Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 38 mo late. Across Maharashtra, 73% kept their date.
How many projects has Panchshil Infrastructure Holdings Pvt. Ltd registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 3 completed on MahaRERA.
Does Panchshil Infrastructure Holdings Pvt. Ltd have MahaRERA regulatory cases?
8 regulatory cases name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology