Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Godrej InfinityP52100003129KeshavnagarmundwaCertificate Signed30 Sep 202030 Sep 2020On date
Godrej RejuveP52100018720KeshavnagarmundwaCertificate Signed30 Mar 202430 Mar 2024On date
Godrej Aqua VistaPM1260002500389MundhawaCertificate Signed19 Mar 203219 Jul 2032+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology