Completion due Mar 2032Mundhawa, Pune 411036 |Promoter: Oxford Realty LLP
Project summary
As registered with MahaRERA
- Buildings
- 7
Location
Coordinates as published by MahaRERA
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 19 Mar 2032
- Registered
- 28 Jul 2025
- Promised
- 19 Mar 2032
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1260002500389 | 28 Jul 2025 | 19 Mar 2032 | — | Oxford Realty LLP | Project page |
7 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Floors with CC | Units |
|---|---|---|---|
| Tower 12 | 17 | 17 | 133 |
| Tower 13 | 31 | 31 | 260 |
| Tower 14 | 31 | 32 | 265 |
| Tower 15 | 31 | 32 | 236 |
| Tower 16 | 29 | 30 | 219 |
| Tower 17 | 29 | 30 | 247 |
| Tower 18 | 29 | 31 | 222 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Documents
1 document held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Mundhawa
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.