Orbit Builders & Developers
Deedo IDDD-TKB7Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 74 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ekvira VishwaP52000011866 | Pen (M Cl) | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | +74 mo* |
Orbit Builders & Developers, in questions
Does Orbit Builders & Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 74 mo late. Across Maharashtra, 73% kept their date.
How many projects has Orbit Builders & Developers registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Orbit Builders & Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.