Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date—no proposed date has passed yet
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Krishna PrabhaP50500054300Nagpur (M Corp.)2024Active31 Dec 2026—On date
Aditya ApartmentP50500076853Nagpur (M Corp.)2024Not reported31 Dec 2026—On date
Abhinav ShilpiP50500080117Nagpur (M Corp.)2025Not reported31 Dec 2027—On date
Sukh SagarPR1190002502631Khamla2026Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Krishna PrabhaOn date
  • Aditya ApartmentOn date
  • Abhinav ShilpiOn date
  • Sukh SagarOn date

Track record notes

  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.