Omkar Enterprises
Deedo IDDD-XPF1Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nutan Omkar ViharP51700029564 | Shirgaon | Certificate Signed | 31 Aug 2022 | 31 Aug 2023 | +12 mo |
| Omkar PlazaP51700045862 | Badlapur (M Cl) | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Shree Datta Narhari ApartmentP51700049472 | Badlapur | Certificate Signed | 1 Dec 2025 | 1 Dec 2025 | +11 mo* |
| Shri Jiveshwar ApartmentP51700056234 | Kulgaon | Certificate Signed | 6 Dec 2028 | 6 Apr 2029 | +4 mo |
Omkar Enterprises, in questions
Does Omkar Enterprises finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Omkar Enterprises registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does Omkar Enterprises have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.