Omkar Enterprises

Deedo IDDD-XPF1

Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late.

Projects44 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay11 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Nutan Omkar ViharP51700029564ShirgaonCertificate Signed31 Aug 202231 Aug 2023+12 mo
Omkar PlazaP51700045862Badlapur (M Cl)Certificate Signed31 Dec 202531 Dec 2025+11 mo*
Shree Datta Narhari ApartmentP51700049472BadlapurCertificate Signed1 Dec 20251 Dec 2025+11 mo*
Shri Jiveshwar ApartmentP51700056234KulgaonCertificate Signed6 Dec 20286 Apr 2029+4 mo

Omkar Enterprises, in questions

Does Omkar Enterprises finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.

How many projects has Omkar Enterprises registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.

Does Omkar Enterprises have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology