Skip to content
Company or firm · first RERA registration 2026

Om Swaminarayan Infra

Deedo IDDD-ANWS

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 1 registration with dates has moved or missed its RERA date

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Aditya Darshan ChsPR1330002502676DombivliCertificate Signed31 Mar 203131 Mar 2031On date

Om Swaminarayan Infra, in questions

Does Om Swaminarayan Infra finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has Om Swaminarayan Infra registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Om Swaminarayan Infra have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology