Om Sai Constructions
Deedo IDDD-E765Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 43 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| SaipuramP52100021427 | Dapodi | Certificate Signed | 30 Apr 2023 | 30 Apr 2023 | +43 mo* |
| Sai TowerPR1260002602095 | Dapodi | Certificate Signed | 31 Dec 2029 | 31 Dec 2029 | On date |
Om Sai Constructions, in questions
Does Om Sai Constructions finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 43 mo late. Across Maharashtra, 73% kept their date.
How many projects has Om Sai Constructions registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Om Sai Constructions have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.