Om Sai Construction
Deedo IDDD-T5WANone of 2 registrations has reached its promised completion date yet.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Ganraj ResidencyP51700054872 | Badlapur (M Cl) | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Shree GayatrideepP51700076836 | Ambarnath | Certificate Signed | 30 Apr 2027 | 30 Aug 2027 | +4 mo |
Om Sai Construction, in questions
Does Om Sai Construction finish projects on time?
None of its 2 MahaRERA registrations has reached its promised completion date yet.
How many projects has Om Sai Construction registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Om Sai Construction have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.