Om Balaji Plaza
Deedo IDDD-W8SHOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 22 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Padmanabh Golden Valley Phase-I Building B And CP52100001995 | Dhayari (Part) | Certificate Signed | 31 Dec 2018 | 30 Oct 2020 | +22 mo |
Om Balaji Plaza, in questions
Does Om Balaji Plaza finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 22 mo late. Across Maharashtra, 73% kept their date.
How many projects has Om Balaji Plaza registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Om Balaji Plaza have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.