Company or firm · first RERA registration 2017
Olympeo Riverside Projects Llp
Deedo IDDD-C81SOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 66 mo late — longer than Maharashtra's 4 mo.
Projects12 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay66 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Olympeo RiversideP52000002351 | Awsare | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Olympeo RiversideP52000012184 | Awsare | Certificate Signed | 30 Jun 2023 | 31 Dec 2028 | +66 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology