Company or firm · first RERA registration 2021

Okay Estate Developers Private Limited

Deedo IDDD-44XS

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases1includes insolvency

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Listed as an NCLT insolvency projectJewel Of Panvel Phase -IListed as NCLT project: JEWEL OF PANVEL PHASE -INot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Jewel Of Panvel Phase -IP52000028505PanvelCertificate Signed30 Jun 202730 Oct 2027+4 mo

Okay Estate Developers Private Limited, in questions

Does Okay Estate Developers Private Limited finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has Okay Estate Developers Private Limited registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Okay Estate Developers Private Limited have MahaRERA regulatory cases?

1 regulatory case name its registrations, including an insolvency (NCLT) case.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology