Nivara Infradevelopers Llp

Deedo IDDD-B25F

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 11 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay11 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Deepanjali co.op hsg society Ltd.P51800020824AndheriCompleted30 Dec 2022—On date
Vileparle Trimbak Sadan Chs LtdP51800052172VileparleLapsed31 Dec 2025—+11 mo*

Nivara Infradevelopers Llp, in questions

Does Nivara Infradevelopers Llp finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.

How many projects has Nivara Infradevelopers Llp registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Nivara Infradevelopers Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology