Nitin Pandurang Kumbhar

Deedo IDDD-TSG4

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay11 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
DeregisteredShree SwarupDeregistered: SHREE SWARUPNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shree SwarupP52000050767WahalCertificate Signed31 Dec 202531 Dec 2025+11 mo*

Nitin Pandurang Kumbhar, in questions

Does Nitin Pandurang Kumbhar finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.

How many projects has Nitin Pandurang Kumbhar registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Nitin Pandurang Kumbhar have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology