Deedo IDDD-VTKROf 15 registrations whose promised date has arrived, 13 kept it (87%). The rest ran a median 30 mo late.
Delivery record
2 of 15 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 15 registrations
15 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Fia Construction Company - Fia PrideP99000000701 | Mahim | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Fia DaffodilsP99000001022 | Mahim | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Fia Construction Company Fia ImperiaP99000003189 | Palghar | Certificate Signed | 30 Oct 2021 | 30 Oct 2021 | On date |
| Fia TulipP99000013698 | Mahim | Certificate Signed | 30 Dec 2022 | 31 Dec 2023 | +47 mo* |
| Fia RegencyP99000013880 | Palghar | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Fia EmeraldP99000013971 | Mahim | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Fia SapphireP99000014626 | Palghar | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Fia OrionP99000015786 | Palghar | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Fia ParadiseP99000015897 | Palghar | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Fia FlorenzaP99000016116 | Palghar | Certificate Signed | 30 Dec 2023 | 29 Dec 2024 | +12 mo |
| Fia Regency AP99000017479 | Palghar | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Fia MeridianP99000023332 | Mahim | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Fia Construction Company A/C Fia EnigmaP99000029742 | Mahim | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Fia Construction Company A/C Fia EnclaveP99000029790 | Mahim | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Fia Construction Company Fia Orion - GrandeP99000032530 | Palghar | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
Show all 15 registrationsShow fewer
Nimish Laxmichand Pasad, in questions
Does Nimish Laxmichand Pasad finish projects on time?
Of 15 MahaRERA registrations whose promised completion date has arrived, 13 kept it (87%). The rest ran a median 30 mo late. Across Maharashtra, 73% kept their date.
How many projects has Nimish Laxmichand Pasad registered with MahaRERA?
15 projects under 15 MahaRERA registrations; 14 completed on MahaRERA.
Does Nimish Laxmichand Pasad have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.