Nilkanth Housaram Kharkar

Deedo IDDD-2D8W

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 55 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay55 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
H R ResidencyP52000021124UlaweCertificate Signed30 Apr 202230 Apr 2022+55 mo*

Nilkanth Housaram Kharkar, in questions

Does Nilkanth Housaram Kharkar finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 55 mo late. Across Maharashtra, 73% kept their date.

How many projects has Nilkanth Housaram Kharkar registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Nilkanth Housaram Kharkar have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology