Nexus Infra
Deedo IDDD-MM2ZOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nexus MeridianP52100013889 | Punawale | Certificate Signed | 31 Jan 2020 | 30 Dec 2020 | +11 mo |
Nexus Infra, in questions
Does Nexus Infra finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Nexus Infra registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Nexus Infra have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.