Deedo IDDD-XBZJOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 66 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Neumec SrushtiRegulatory order: PROJECT NAME: NEUMEC SRUSHTI (Regulatory Case No. 385 OF 2025) dated 30 June, 2025. | 30 Jun 2025 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Neumec SrushtiP51800002532 | Kurla | Certificate Signed | 30 Jun 2022 | 31 Dec 2027 | +66 mo |
| Neumec godawariP51800005145 | Vileparle | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
Neumec Estate Developer Llp, in questions
Does Neumec Estate Developer Llp finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 66 mo late. Across Maharashtra, 73% kept their date.
How many projects has Neumec Estate Developer Llp registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Neumec Estate Developer Llp have MahaRERA regulatory cases?
1 regulatory case name its registrations.