Company or firm · first RERA registration 2021

Nestcon

Deedo IDDD-7J07

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 8 mo late.

Projects55 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay8 mowhen late
First sales on record48registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 5 registrations with dates moved or missed their RERA date · months late against the original promise

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
SwarupnaliniP52100031704KothrudCertificate Signed31 Dec 202431 Dec 2024On date
Reshma Heights Co-Operative Housing Society Ltd.P52100051614KothrudCertificate Signed31 Dec 202531 Dec 2025On date
RavikesharP52100052392KothrudCertificate Signed31 Dec 202531 Dec 2025+11 mo*
Anamay ApartmentsP52100054508KothrudCertificate Signed31 Dec 202631 Dec 2026On date
PakharP52100080564PethCertificate Signed30 Apr 202830 Aug 2028+4 mo

Nestcon, in questions

Does Nestcon finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.

How many projects has Nestcon registered with MahaRERA?

5 projects under 5 MahaRERA registrations; 2 completed on MahaRERA.

Does Nestcon have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.