Nest Krisala Associates
Deedo IDDD-C714Of 2 registrations whose promised date has arrived, 2 kept it (100%).
Delivery record
None of 2 registrations with dates has moved or missed its RERA date
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| AdoraP52100003141 | Ravet | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| AdoraP52100016201 | Ravet | Certificate Signed | 20 Oct 2020 | 20 Oct 2020 | On date |
Nest Krisala Associates, in questions
Does Nest Krisala Associates finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Nest Krisala Associates registered with MahaRERA?
1 project under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Nest Krisala Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.