Deedo IDDD-CVS8Of 1 registration whose promised date has arrived, 1 kept it (100%).
Delivery record
None of 1 registration with dates has moved or missed its RERA date
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Arni AtlanticaP52800023809 | Aghari | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
Neeta Tushar Gadhave, in questions
Does Neeta Tushar Gadhave finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Neeta Tushar Gadhave registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Neeta Tushar Gadhave have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.