Navnirrmitii Builders And Developers LLP
Deedo IDDD-WTCBNone of 2 registrations has reached its promised completion date yet.
Projects22 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record
Delivery record
None of 2 registrations with dates has moved or missed its RERA date
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Navnirrmitii SquarePM1300002602143 | Karanje Tarf Satara (Ct) | Certificate Signed | 31 Dec 2030 | 31 Dec 2030 | On date |
| Nirav HeightsPM1300002602442 | Khed (Ct) | Not on record | 31 Dec 2030 | — | On date |
Navnirrmitii Builders And Developers LLP, in questions
Does Navnirrmitii Builders And Developers LLP finish projects on time?
None of its 2 MahaRERA registrations has reached its promised completion date yet.
How many projects has Navnirrmitii Builders And Developers LLP registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Navnirrmitii Builders And Developers LLP have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology