Skip to content
Company or firm · first RERA registration 2019

Navkar Construction

Deedo IDDD-X88B

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 17 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay17 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Silver Oaks VillasP51500020485Satara (Ct)Completed20 Apr 2022—On date
K P HeritageP51500027076Satara (Ct)Certificate Signed1 May 20251 May 2025+17 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology