Namrata Developers

Deedo IDDD-0J9Q

Of 7 registrations whose promised date has arrived, 7 kept it (100%).

Projects88 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record9registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 8 registrations with dates moved or missed their RERA date · months late against the original promise

8 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
AikonicP52100004720Talegaon Dabhade (R)Certificate Signed1 Sep 20191 Sep 2019On date
Namrata Business CentreP52100017272Talegaon Dabhade (R)Certificate Signed30 Dec 202130 Dec 2021On date
Happycity TalegaonP52100017513Talegaon Dabhade (R)Certificate Signed30 Dec 202230 Dec 2022On date
Namrata MagicP52100018637Pimpale SaudagarCertificate Signed30 Oct 202030 Oct 2020On date
AikonicP52100028284Talegaon Dabhade (R)Certificate Signed31 Jan 202331 Jan 2023On date
Aikonic 3P52100028578Talegaon Dabhade (R)Certificate Signed30 Sep 202330 Sep 2023On date
Namrata Prime LandP52100032630Talegaon Dabhade (R)Certificate Signed29 Jun 202529 Jun 2025On date
Namrata ManifestaP52100080124PunawaleCertificate Signed30 Dec 202930 Apr 2030+4 mo

Namrata Developers, in questions

Does Namrata Developers finish projects on time?

Of 7 MahaRERA registrations whose promised completion date has arrived, 7 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Namrata Developers registered with MahaRERA?

8 projects under 8 MahaRERA registrations; 7 completed on MahaRERA.

Does Namrata Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology